"La Cuisine" temporary theatre

Local authorities

Types of mandate

Architectural design and direction
(Directed by Spantech)
Stage engineer G. Vadas

Dates

Building permit: December 2017
Construction site timeline: March - August 2018

Technical
informations

1,375 m2 GFA (Theatre and foyer with annex)
14,481 m3 SIA
540 seats

Location

Carouge

Collaborators

A. Micoud

 

Project

Following an architectural bid, the former Carouge theatre was to be demolished. For the ensuing construction phase, a temporary solution had to be found. This is how the opportunity arose to develop the project of an ephemeral structure, called “La Cuisine”, on a site left bare in the centre of the Praille-Acacias-Vernets perimeter. The structure will be dismantled and resold after two seasons of shows on the temporary site.

540

seats for shows

337m2

of stage,
the largest theatre set in Geneva 
after the Grand-Théàtre

10

metal portal frames 22m50 long by 12m high 
supporting the roof of the theatre